The physical progress of the works on section 4 of the Sibiu-Pitești motorway has reached 82%, announced on Sunday the general director of the National Company for the Administration of Road Infrastructure (CNAIR), Cristian Pistol. ‘The pouring of road concrete in the first gallery (Pitești-Sibiu direction) of the Momaia tunnel has been completed. The pouring […]
The works on the Suplacu de Barcău – Chiribiș highway section of the Transylvania Highway are a little ahead of schedule, with the physical degree of execution being around 55%, said contractor Cristian Erbașu on Saturday at a conference on construction topics. He assured that the completion deadline will be respected, at most it could […]
Romania can currently boast 1,280 kilometers of highways and expressways, with over 800 kilometers under construction, and another 500 kilometers in the design stage, said on Tuesday, the Secretary of State in the Ministry of Transport and Infrastructure, Cristian Șologon, at the official opening of the Bucharest Auto & Accessories Show 2025. ‘This show is […]
The Minister of Transport, Ciprian Șerban, announced on Thursday that the completion and commissioning of the last section of the Craiova-Pitești expressway (DEx 12) marked ‘an essential stage for Romania’s road infrastructure’. The Minister was present, before the opening of traffic, in the area of the connection between DEx 12 and the A1 motorway, in […]
The execution of the Chiribiș – Biharia section of the Transilvania Motorway is officially unblocked, the National Road Investment Company has issued the Start Order, and the works can start as early as July 24, almost 6 months before the contractual deadline, the Ministry of Transport and Facebook announced on Wednesday. ‘The execution of the […]
Porr Construct has been named the winner of the contract for the construction of lot 2 (Jebel – Moravița) of the Timișoara – Moravița Motorway (A9), announced on Monday the general director of the National Road Infrastructure Management Company (CNAIR), Cristian Pistol, on his Facebook page. ‘Important stage in the development of the road infrastructure […]
The National Road Investment Company has launched over 400 kilometers of highway on the main corridors of the country, has three objectives in design and another six in the design and execution phase, all of which totaling over 50 billion lei, said on Wednesday, the general director of CNIR, Gabriel Budescu, at the conference ‘Italy […]
The Romanian-Bulgarian partnership has reached a physical stage of 98.6% of the works on the Mizil-Pietroasele section of the Moldova Motorway, announced on Friday the Minister of Transport and Infrastructure, Sorin Grindeanu, on his Facebook page. In his opinion, this year it will be possible to drive at least from Focșani to Adjud (49 km), […]
The National Road Investment Company (CNIR) has awarded the Ditrău – Grinţieș lot, the longest lot of the Unirii Motorway, to an association of builders from Romania and Bosnia, for the amount of 6.14 billion lei (excluding VAT), announced the Minister of Transport and Infrastructure, Sorin Grindeanu, on Monday. ‘CNIR has awarded another contract for […]
The Pitești – Curtea de Argeș section of the Sibiu – Pitești motorway (A1) is nearing completion, announced on Wednesday the general director of the National Road Infrastructure Management Company (CNAIR), Cristian Pistol. ‘The Pitești – Curtea de Argeș section of the Sibiu – Pitești motorway (A1) is nearing completion! On the last 15 km […]
The physical progress on the construction site of Lot 1 Focsani – Domnești Târg of the Focsani – Bacău (A7) motorway has reached 42%, with traffic to be opened by the end of the year, announced on Wednesday the general director of the National Road Infrastructure Administration Company (CNAIR), Cristian Pistol. ‘Good pace of work […]
Four Associations, which include builders from Romania, Bulgaria and Turkey, have submitted bids for the construction of Lot 1, 10.3 km long, of the Craiova – Filiași highway, which will also function as a bypass for the northern area of Craiova, announced on Monday the Minister of Transport and Infrastructure, Sorin Grindeanu. ‘Today, four Associations, […]
The contract for the construction of a new section of the Unirii Highway (#A8) is entering the tender procedure, announced the Minister of Transport, Sorin Grindeanu, on Friday. ‘CNIR has submitted the documentation for the design and execution of the Târgu Frumos-Lețcani section (28.8 km) for validation to ANAP. After the validation of the documentation, […]
A Romanian company has won the contract for the design and construction of the Pipirig – Vânători Neamț (Leghin) lot of the Târgu Mureș-Târgu Neamț motorway section, announced the Minister of Transport, Sorin Grindeanu, on Monday. ‘The constructor for another lot of the A8 (Union Motorway) has been appointed. A Romanian company has won the […]